Solar Fiber
Data / Fiber
- Receive, terminate & OTDR test cables on reels prior to installation
- Installation of approx. 20,000’ of 12-strand, single-mode, direct-burial cable
- Fusion splice & terminate fiber loop at 11 PV inverter skids
- Installation of approx. 3,500’ of 96-strand, single-mode in interduct from utility substation to site SCADA
- Complete fiber DB loss testing
Location: Simsbury, CT
Engineering: Plan and Spec
Market Sector: Data / Fiber, Renewable Energy
Year started: 2019
Duration: 2 Months