AC-Coupled Energy Storage System
Renewable Energy
- Installation of 2-15kV medium-voltage URD circuits from existing vault to new energy storage system
- Installation of underground AC, DC & DAS conduits for BESS & balance of plant equipment
- Installation of site ground grid
- Installation of 1320kw PCS
- Installation of 49’ IHI battery energy storage container
- Installation of 360 Lishen batteries
Location: Amherst, MA
Engineering: Plan and Spec
Market Sector: Renewable Energy, Energy Storage
Year started: 2019
Duration: 3 Months